Project Name:Delivery of 4×1266m³/min Blue Carbon Tail Gas Screw Compressor Units
Location:Xinjiang, China
Date:June 2025
Overview:
The company successfully delivered four 1266m³/min blue carbon tail gas screw compressor units for Xinjiang Jiaguo Weiye New Energy’s 600,000 t/y coal tar hydrogenation project. This achievement marks a breakthrough in the industrial application of ultra-large flow process screw compressors.
Blue carbon tail gas contains hydrogen, methane, carbon monoxide, and carbon dioxide, mixed with tar, dust, and sulfur compounds. As a flammable and toxic gas, it imposes stringent requirements on compressor reliability and technology.
Highlights:
Ultra-High Capacity: Each unit compresses up to 250,000 Nm³/h of blue carbon tail gas.
Process Adaptability: Engineered for dust-, acid-, and tar-laden gases.
High Reliability: Supports continuous operation up to 24,000 hours.
Innovative Design: Developed with Kaishan’s proprietary large-flow compression technology.
This project demonstrates Kaishan’s capability to deliver reliable, high-efficiency compression solutions for complex coal chemical applications.
Project Background:
Part of Xinjiang’s “14th Five-Year Plan” key construction projects, the facility represents a total investment of RMB 7.3 billion and covers 1,700 mu.
Main outputs include:
3.6 million t/y blue carbon
600,000 t/y naphtha, diesel, LPG, coal pitch
180,000 t/y LNG
350,000 t/y methanol & acetic acid